Jindabyne Shared Trails Section 2.1
Business Name
Snowy Monaro Regional Council
VP Reference #
VP468545
Opens
Wednesday 16 July 2025
(AUS Eastern Standard Time)
Closes
Thursday 28 August 2025 04:00 PM
(AUS Eastern Standard Time)
CLOSED
Supplier query cut-off
Thursday 21 August 2025 04:00 PM
(AUS Eastern Standard Time)
Expected decision
Thursday 25 September 2025
(AUS Eastern Standard Time)
Buyer Details
Business Name
Snowy Monaro Regional Council
Location
81 Commissioner St
Cooma, New South Wales 2630
Australia
WebSite:
https://www.snowymonaro.nsw.gov.au/
Business Info
Snowy Monaro Regional Council encompasses a region that is proud of its history. The Snowy Monaro Regional Council acknowledges that Aboriginal people – the Ngarigo, Walgalu and Southern Ngunnawal – are the original inhabitants and remain the custodians of where we live.
We are also a culturally diverse region, thanks to the Snowy Scheme which saw over 100,000 people from over 30 countries coming to work on the scheme. To this day the Region enjoys the benefits of our cultural diversity.
The region is home to 20,707 people and reflects a degree of cultural diversity that has its roots in agriculture, early gold mining, the Snowy Mountains Scheme, timber logging and skiing industries.
Contact Details
The buyer has elected to have their personal and contact details hidden. These details will be revealed at the buyers discretion.
What the buyer is requesting
Details
Section 2.1 identified as Tyrolean Village to East Jindabyne which is a construct only package of works.
• Construct the works in accordance with the approved design and relevant standards.
• Provide a detailed breakdown of anticipated maintenance costs of the completed trail works.
• Implement a suitable quality management system throughout all stages of the project.
• Maintain the finished product throughout the 12 months defects liability period
Background information / Compatibility requirements
Details
See attached Technical Specification
Desired Outcomes ('Nice to haves', Conditions & Warranties, SLA's, Project benefits)
Details
See attached Technical Specification
Supplier lists selected
Lists
Building Trade, Repairs, Maint.
Construction & Operation
Horticulture & Arboriculture
Categories selected
Categories
Building Trade & Repairs & Maintenance Services
1: Landscaping
Construction & Operation
1: Building Construction Materials & Services
2: Other Civil Construction Materials & Services
3: Track & Trail Construction
Horticulture & Arboriculture
1: Landscaping Design & Architecture Services
Regions of Service
Locations
Australian Capital Territory
1: ACT (all other areas)
2: Canberra
New South Wales
1: Illawarra
2: Murray
3: Murrumbidgee
4: South Eastern
5: Sydney
All Regions of Service locations are within Australia.
Information requested by others
16/Jul/2025 07:34 PM
Question
:
Looking to see what my options are if my team is not available to make the manadatory project briefing.
My team will be on a previously commited job on the proposed date however we are very keen to complete a briefing and submit a response.
thanks, Lachy, TRC Trails
Answered on 22/Jul/2025 09:36 AM
:
Due to requests for an alternative mandatory inspection date, an additional inspection date has been added: FRIDAY 25/07 AT 11:00AM. The meeting point will be at the intersection of Kosciuszko Rd & Jerrara Drive, East Jindabyne. The meeting on Monday 28/07 will also still go ahead.
22/Jul/2025 10:51 AM
Question
:
Wild Tracks intends to attend the tender meeting on Monday.
Questions:
Can you confirm the total track length of the work area for 2.1?
Can you confirm the percentage of the work area where gravel is to be laid?
Answered on 24/Jul/2025 03:32 PM
:
1. The length of trail for section 2.1 is 3,675m
2. The trail is to comprise a cleared width of 2m (so approx. trail are of 7350m2), with a formed and compacted trail width of 1.5m comprising site material (5,512.50m2)
Where there are soft spots, either;
a) replace with imported material
b) treat with geogrid
c) consider drainage arrangement to assist with areas drying out.
Gravel/DGS20 material may be required in isolated sections with steep grades to assist with stabilization and at bridge approaches to reduce erosion. Estimate this to be for maximum 10% of the overall alignment. Where required gravel should be minimum 75mm thick compacted to 98% MMDD. Considering the above trail length this equates to 370m (L) x 1.5m (W) = 555m2 x 0.075m (D) = 41.6m3 of DGS material.
23/Jul/2025 05:37 PM
Question
:
Can you please clarify as to why the documents noted in the Notice of Determination ADM_01 Approved Plan & Documents are different to the other Volume 3 Tender Documents provided in Vendor Panel?
Answered on 19/Aug/2025 10:19 AM
:
Correct documents have now been uploaded as part of the addenda package.
27/Jul/2025 04:00 PM
Question
:
In relation to Section 2.1, the General Notes on drawing 50522007-C-2002/3/4 (Stantec) specify requirements that are uncommon with typical trail construction.
- Set out by Surveyor. We assume coordinates will be provided as part of the detailed design (by others). Please confirm if set-out by handheld GPS is sufficient.
- Existing Services. Is ground scanning and potholing required, or is desktop evaluation via BYD sufficient? If scanning / potholing / hand excavation is required, please clearly nominate locations. General notes state existing services have been plotted, however nothing is shown.
- Military Base. Please confirm there is no military / restricted zones.
- Sediment control. Please confirm that filters to sumps, straw bales and silt/sediment fencing is not required.
- Stabilised access point. Please confirm this is not required (ballast rock, shaker pad, drainage etc).
Thank you
Answered on 19/Aug/2025 10:19 AM
:
Set out by surveyor: CAD/shape files have now been provided with the addenda documents.
Existing services: BYD should be carried out at a minimum. Contractors must satisfy themselves that there are no underground services.
Military base: this has now been removed, apologies for any confusion.
Sediment control: sediment/erosion control requirements have been updated in the addenda documents.
28/Jul/2025 09:13 PM
Question
:
Hi Team,
Thank you for the site visit today, two very exciting projects!
Can you please confirm that Professional Indemnity is required for both 2.1 and 1.1 & 2.2 tenders?
Can you also confirm the amount for each is correct as one states $10m and the other is $20m.
Thanks
Answered on 29/Jul/2025 11:16 AM
:
Professional Indemnity is required for all tender packages to a value of $10 million.
Updates made to this Request
16/Jul/2025 01:16 PM
Please note: The following addendum has been recently added.
1. Added: (Addendum) Volume 5 AS 4000-1997 General Conditions of Contract DRAFT.docx
Please consider this addendum when responding.
07/Aug/2025 09:30 AM
We are working on getting the updated documents online shortly. You will receive a notification when this happens. In the meantime we have extended the tender by two weeks.
12/Aug/2025 04:18 PM
Please note ALL attachments have been amended and updated.
Make sure you are looking at the updated volume when responding to this tender as all volumes have been updated.
The tender has been extended until August 28 2025.
14/Aug/2025 11:25 AM
Please note: The following addenda have been recently added.
1. Added: (Addendum) Vol_3 Stamped Supporting Documents_ 2.1- part 1.pdf
2. Added: (Addendum) Vol_3 Stamped Supporting Documents_ 2.1- part 2.pdf
3. Added: (Addendum) Vol_3 Stamped Supporting Documents_ 2.1- part 3.pdf
4. Added: (Addendum) Vol_3 Stamped Supporting Documents_ 2.1- part 4.pdf
5. Added: (Addendum) Stamped Approved Plans_PAN-427143 SECTION 2.1 (1).PDF
Please consider these addenda when responding.