Tender Details
Wentworth Street, Bellerive - Stormwater Upgrade
Business Name
City of Clarence
VP Reference #
VP524174
Buyers Reference #
T1586-25
Opens
Saturday 05 September 2026 (Tasmania Standard Time)
Closes
Wednesday 21 October 2026 04:00 PM (Tasmania Standard Time)
Supplier query cut-off
Wednesday 14 October 2026 04:00 PM (Tasmania Daylight Time)
Expected decision
Wednesday 02 December 2026 (Tasmania Standard Time)
Buyer Details
Business Name
City of Clarence
Location
38 Bligh St
Rosny Park, Tasmania 7018
Australia
WebSite:
https://www.ccc.tas.gov.au/
Business Info
Clarence City Council (or City of Clarence) is a local government body in Tasmania, and one of the five municipalities that constitutes the Greater Hobart Area. The Clarence local government area has a population of 56,945, covering the eastern shore of the Derwent River from Otago to the South Arm Peninsula and the smaller localities of Cambridge, Richmond, and Seven Mile Beach.

The administrative centre and main commercial district of Clarence is Rosny Park, approximately 5 kilometres from the CBD of Hobart. Bellerive Oval lies immediately to the south, and the Hobart International Airport is located further north-west along the Tasman Highway.
Contact Details
The buyer has elected to have their personal and contact details hidden. These details will be revealed at the buyers discretion.
What the buyer is requesting
Details
Wentworth Street, Bellerive - Stormwater Upgrade

T1586-25

Tenders are invited from suitably qualified Contractors for the above.

A pre-tender site briefing is scheduled for 10:30am on Wednesday 16 September 2026, on site. Attendance is recommended but is not mandatory. Please register your interest with the contact officer for the pre-tender site briefing.

Tender responses are to be submitted electronically via Council’s Vendor Panel portal, or via email to tenders@ccc.tas.gov.au and with the description and tender number (T1586-25) clearly marked, until 3.00pm AEDT on 7 October 2026.

Tender documents will be available by downloading from Vendor Panel www.vendorpanel.com.au/clarencecity/tenders or by contacting Procurement on (03) 6217 9500 or procurement@ccc.tas.gov.au

Neither the lowest nor any tender will necessarily be accepted. Late tenders will not be considered.

For further information, please contact Procurement on (03) 6217 9500 or procurement@ccc.tas.gov.au
Attachments to this Request
Documents
12
Supplier lists selected
Lists
  • Construction & Operation
Categories selected
Categories
  • Construction & Operation
    1: Drainage Services
    2: Excavation Services
    3: Other Civil Construction Materials & Services
    4: Pipes & Fittings Services
    5: Road Building Products & Maintenance & Services
    6: Underground Services
Regions of Service
Locations
  • Tasmania
    1: Southern

All Regions of Service locations are within Australia.
Information requested by others
24/Sep/2026 09:15 AM
Question:
With reference to the Section 4 of the RFT regarding working hours and traffic limitations, the available working times on Clarence Street are to be limited between 9am – 2:30pm, with extended working hours accepted on Clarence Street to 9pm. We have therefore interpreted the available working hours as 9am – 2:30pm and 6:30pm – 9pm. Due to the limited working windows (max 5.5 hours) can you please confirm if nightworks would be permitted?

Answered on 30/Sep/2026 08:11 AM:


Good Morning,

Work between 9pm and 7am is unlikely to be approved except in exceptional circumstances due to the impact those works have on the local residential community.

There may be an opportunity during state school holidays to reduce the hours where lane closure restrictions apply on Cambridge Road as traffic volumes decrease during school holidays.

The final date for Practical Completion has been extended from 18 December 2027 to 4 February 2028 to increase the time available to work during school holidays.
24/Sep/2026 11:47 AM
Question:
Can the principle confirm if any works can be completed outside the nominated work hours?

That is, work being completed between 9pm to 7am.

Answered on 30/Sep/2026 08:12 AM:


Good Morning,

Work between 9pm and 7am is unlikely to be approved except in exceptional circumstances due to the impact those works have on the local residential community.

There may be an opportunity during state school holidays to reduce the hours where lane closure restrictions apply on Cambridge Road as traffic volumes decrease during school holidays.

The final date for Practical Completion has been extended from 18 December 2027 to 4 February 2028 to increase the time available to work during school holidays.
Updates made to this Request
10/Sep/2026 11:18 AM
Submission close time has been updated from 3pm to 4pm to match the tender documentation.

22/Sep/2026 09:51 AM
Please note: The following attachment has been recently added.

1. Added: Addendum No.1 - T1586-25 Wentworth Street Stormwater Upgrade.docx

Please consider this attachment when responding.

24/Sep/2026 01:50 PM
Please note: The following attachment has been recently added.

1. Added: Addendum No.2 - T1586-25 Wentworth Street Stormwater Upgrade.docx

Please consider this attachment when responding.