Tender Details
EOI for Wivenhoe OT Network - Detailed Network Design and Support Services
Business Name
CleanCo QLD
VP Reference #
VP472087
Buyers Reference #
CCQ-096-25
Opens
Monday 04 August 2025
(E. Australia Standard Time)
Closes
Monday 01 September 2025 06:00 PM
(E. Australia Standard Time)
CLOSED
Supplier query cut-off
Monday 25 August 2025 06:00 PM
(E. Australia Standard Time)
Expected decision
Monday 13 October 2025
(E. Australia Standard Time)
Buyer Details
Business Name
CleanCo QLD
Location
300 George St
Brisbane City, Queensland 4000
Australia
WebSite:
https://www.cleancoqueensland.com.au/
Business Info
CleanCo Queensland is a government-owned electricity generation and trading company - fuelled by a mix of renewable energy and innovative energy solutions.
Contact Details
The buyer has elected to have their personal and contact details hidden. These details will be revealed at the buyers discretion.
What the buyer is requesting
Details
This is a call for expressions of interest only and is intended to assist the Customer to understand the capability of the market to meet the Customer’s objectives and requirements to identify potential suppliers in the market.
CleanCo is conducting an upgrade project to refurbish the Wivenhoe Power Station Operational Technology (OT) network architecture.
The Wivenhoe Power Station control system network was developed in the first decade of this century and whilst functional requires significant refurbishment to meet contemporary control system network practices and CleanCo’s responsibilities under the AESCSF and associated legislation.
CleanCo seeks to develop a new network architecture for Wivenhoe Power Station, based on a high-level design that had been developed and the requirements borne from a similar upgrade project underway at one of CleanCo’s other generation sites.
The high-level objective is to introduce a level of standardisation across CleanCo hydro-fleet for the control system network design whilst accounting for site specific requirements.
In scope:
The scope of this body of work is to provision the development of an OT Network Detailed Design and with the follow-on project phases (testing, installation and commissioning). The scope of works is divided into two non-separable portions, which at a high level are:
1. "Portion 1A" (Fixed Price) – Development of a Detailed Network Design from the High-Level Design and reflect inputs from the CleanCo’s engineering team and external contractors. This portion is the bulk of the project and consists of largely front-end engineering and design (FEED) works to develop the Detailed Network Design.
2. "Portion 1B" (Schedule of Rates) – Provision of ongoing design input, assistance and support to the works for the remainder of the project, though having the Detailed Network Design team available on an as-required basis to update the design and guide the works to a successful completion.
Background information / Compatibility requirements
Details
Experience is delivering similar requirements in CleanCo's industry sector is essential.
See attached files for further details.
Questions asked by the buyer
Question 1 - [Required]
Please confirm that you have read the attached EOI documentation pack and attach the Response Form in the prescribed format as part of your submission.
Question 2 - [Required]
Works in scope of this EOI are to be carried out in compliance with all applicable Commonwealth and Queensland State legislative requirements and codes of practice.
Because the works would be delivered in Queensland, interested suppliers must be able to provide Registered Professional Engineer of Queensland (RPEQ) supervision and approval (in accordance with the requirements of the Queensland Professional Engineers Act 2002) of all works conducted under this scope of works.
Please confirm compliance to this requirement as part of your submission.
Supplier lists selected
Lists
Engineer, Research, Tech services
IT & Telecomms
Power Generation, Trans & Distrib.
Categories selected
Categories
Engineering & Research & Technical Based Services
1: Engineering Consulting Services
IT & Telecomms
1: Services - Industry Sector Expertise
Power Generation & Transmission & Distribution
1: Power Generation Systems
Regions of Service
Locations
Queensland
1: Brisbane
All Regions of Service locations are within Australia.
Information requested by others
05/Aug/2025 03:10 PM
Question
:
Can you provide clarity to the "Security Questionnaire", item A.21 in Part B-EOI Supplier Response form? Reference to a Questionnaire does not appear in the other supplied documents/parts/attachments.
Answered on 06/Aug/2025 01:37 PM
:
Thank you for your observation. The Security Questionnaire has not been included in this EOI stage. Suppliers can disregard this question A.21 in tab "0. Details and Certification", this item will not be marked.
05/Aug/2025 03:22 PM
Question
:
Can you provide clarity and parameters around Product Liability insurance, Item C.2 in Part B - EOI Supplier Response Form? The product of the future request is a Design for Network Architecture, not a product to do harm. Product liability insurance is not listed in Schedule 1 - Part C - Professional Services Agreement (items #6-9).
Can you provide clarity and parameters around Agreement Particulars for Cyber Security insurance, Item C.5 in Part B - EOI Supplier Response Form? Cyber Security insurance is not listed in Schedule 1- Part C - Professional Services Agreement (items #6-9).
Answered on 06/Aug/2025 01:41 PM
:
Suppliers are invited to list their current insurances in section C of tab "0. Details and Certification", Part B - EOI Supplier Response Form. Part C - Professional Services Agreement is a template only at this stage. The agreement will be developed with the successful supplier at a later stage, following the completion of this EOI stage, and any subsequent RFQ/RFP stage.
11/Aug/2025 08:47 AM
Question
:
Good morning - Based on Part B EOI Supplier Response A.21, it states "Have you submitted your responses to the Security Questionnaire?" however there are no separate attachments nor mention of said questionnaire within the RFT documents.
Could CleanCo please advise where to locate the questionnaire so that we can review.
Answered on 25/Aug/2025 11:09 AM
:
Thank you for your observation. The Security Questionnaire has not been included in this EOI stage. Suppliers can disregard this question A.21 in tab "0. Details and Certification", this item will not be marked
11/Aug/2025 04:24 PM
Question
:
Dear Alister,
We understand that this request is an EOI, but could you clarify whether the subsequent tender will cover ongoing management and support for the network, security infrastructure, and end-user equipment, or if it will be limited to the design and delivery of these services?
Thanks.
Answered on 25/Aug/2025 11:12 AM
:
Please refer to the in-scope and out-scope portions indicated in the EOI and SOW documentation.
12/Aug/2025 03:14 PM
Question
:
Q1: Regarding section 3.4 Budget Estimate, you have requested a budget estimate for delivering the detailed network design, however the drawing are not currently available, is it possible to share the drawings as detailed in Section 5: Principal Furnished Technical Data of WI24011 - Statement of Works Wivenhoe OT Network.
Q2. Regarding 3.1 Project Schedule, You have provided a high level timeline of the project deliverables, please advise what further information do we need to include in our response.
Answered on 25/Aug/2025 11:17 AM
:
At this stage, a high-level budget estimate supported with assumptions will be adequate. Pricing will be evaluated in a subsequent stage of the procurement process, following this EOI.
14/Aug/2025 05:36 PM
Question
:
To assist with the pricing, we would like to know if the Wivenhoe OT Network High Level Design document is already available, and if so, can it be provided to us at this stage?
Answered on 25/Aug/2025 11:14 AM
:
This document may be supplied to suppliers in a subsequent stage of the procurement process, following this EOI.
15/Aug/2025 02:22 PM
Question
:
SOW refers to the following documents to be read in conjunction with the SOW but they are not supplied on the tender portal, can the current versions of the following documents be supplied?
- CCQ-ENG-ELE-STD-001 - Electrical Engineering Standard IED Communications
- CCQ-AO-ELE-STD-001 - Electrical Safety Standard
- AO-PRO-CleanCo Drawing Management Procedure
Answered on 25/Aug/2025 11:13 AM
:
CleanCo may provide the additional documentation to suppliers in a subsequent stage of the procurement process, following this EOI.
Updates made to this Request
06/Aug/2025 01:33 PM
A question has been added to confirm the supplier's compliance to requirements of the Queensland Professional Engineers Act 2002.
25/Aug/2025 10:26 AM
The closing date for this EOI has been extended by 1 (one) week to 1 September 2025 6:00 PM.